Project Scheduler Resume
0/5 (Submit Your Rating)
Brenham, TexaS
SUMMARY:
- Analyze systems and processes and implement infrastructure improvements. Self - directed, disciplined, and confident leader and vibrant team player who delivers exceptional rather than expected results through strategic thinking, innovative problem-solving, and managing teams for performance excellence.
- Production Planning - Inventory Management - Site Operations Management
- Staff Development & MRP - Material Planning Sys Supply Chain Management
TECHNICAL SKILLS:
SKILLS: SAP JD Edwards Visual Manufacturing APCS Production SchedulingOracle ExcelMS Office
PROFESSIONAL EXPERIENCE:
Project Scheduler
Confidential
Responsibilities:
- Prepare project schedule on primavera P6 with WBS, activities and milestones
- Run Primavera Project planner reports and analysis (v-lookup, concatenate, pivot tables)
- Update schedules when required
- Run Filters on the primavera Planner for reports required by management
- Prepare Logic Diagrams, bar charts and histograms
- Analyze and mitigate schedules for impacts
- Prepare Critical Path Method (CPM) schedules as required
- Perform cost to complete projections and earned value
- Lead project status meetings with project team and stakeholders
- Support the project team in the development of Project Change Notices.
- Create project plans by identifying tasks to be performed, necessary requirements, deliverables and milestones.
- Demonstrate skill in defining project scopes and details and devising and recommending alternative methods of standardized analysis as a basis for solving problems.
- Manage data and information collection and research.
- Analyze, compare and forecast current status against established baseline schedule
- Monitor and evaluate results in alignment with project goals and objectives.
Project Controls Specialist (Senior Project Scheduler)
Confidential
Responsibilities:
- Analyzed potential and existing large to mega-projects in each region/franchise for conflicts pertaining to scheduling, personnel/manning needs, contractor availability, and equipment availability.
- Recommend course of action necessary to resolve aspects of projects noted to be problematic to successful project/program completion.
- Interfaced with various stakeholders to receive project progress updates to determine schedule impacts using critical path methodology (CPM)
- Maintained master project schedule and provide progress updates as required for project reporting
- Identify critical project metrics to track in order to monitor progress
- Issue bi-monthly progress reports for each Operating Area noting aspects of concern and internal/external resources available
- Attend project and stakeholder meetings as needed
- Reviewed client and sub-contractor schedules
- Query cost and schedule forecasts (v-lookup, concatenate, pivot tables)
- Performed job audits to validate actual progress vs. reported
- Provide cost and schedule forecasts
- Create, Edit, and Maintain full level 3 schedules with resources and cost loaded
- Ensure project activities are logically tied - provide sequencing recommendations
- Make presentations to clients/stakeholders on project controls
- Perform project closeout with summary cost and schedule statistics
- Prepare S-curves highlighting cumulative progress vs. baseline
Senior Project Scheduler
Confidential
Responsibilities:
- Generate and maintained project work package schedules based on inputs from work package and or cost managers
- Support the development and maintenance of scheduling templates for creating lower tier work package schedules that feed into the integrated master schedule.
- Performed schedule analyses to identify critical path, probability of meeting milestones and opportunities for increasing schedule margins.
- Support the establishment of processes and procedures for generating and maintaining the Integrated Master Schedule.
- Developed and analyzed schedule data at the task level and cost accountant level for each WBS and OBS.
- Performed schedule variance assessments and supports the issuance and maintenance of work packages and planning packages (v-lookup, concatenate, pivot tables)
- Create, Edit, and Maintain full level 3 schedules with resources and cost loaded using P6
- Ensure project activities are logically tied - provide sequencing recommendations
- Interfaced with various stakeholders to receive project progress updates to determine schedule impacts using critical path methodology (CPM)
Planner/Scheduler
Confidential
Responsibilities:
- Developed detailed project schedules and maintaining the master schedule for all projects. (Engineering and supply chain)
- Reports to the project manager (PM) project progress and identifying critical deliverables in relation to the baseline project schedule to identify potential risks to the project (v-lookup, concatenate, pivot tables)
- Identify and report to the project manager - project related required resources and resource deficiencies for each project throughout the project
- Create, maintain, and diagnose problems with WBS and project calendars in P6
- Maintain project schedule reporting using P6 to update project status for
- TLP’s, jack ups, masts, land rigs and various FPSO packages
- Liaise with contractor/outsourcing representatives for various projects to ensure compliance to the overall project schedule
- Lead project related meetings to inform stakeholders project progress versus the original baseline schedule
- Consult and advise PM’s and senior management of critical items, project milestones and continuing progress of their related projects.
- Initiate recovery plans to mitigate risk and minimize the impacts from adverse changes in the project schedule with various project stakeholders.
- Forecast data for possible future projects in regards current backlog versus future backlog and possible constraints and or bottlenecks
- Determined reporting and analysis needs, and sets up and prepares special and periodic reports of project activities using S-curves, earned value and various P6 report tools.
Materials Manager/Master Scheduler
Confidential - Brenham, Texas
Responsibilities:
- Manage department and oversee all project scheduling and production control activities that are responsible for 50MM annual revenue.
- Level loaded plant capacity to maximize use of available labor and material to reflect the lean manufacturing process to maximize the shop production and efficiency.
- Monitor actual production and material consumption against the schedule to include order coordination, capacity requirements, supply inventory analysis etc. Investigate variances against schedules and alert management as deemed appropriate.
- Managed direct planning activities including the proper management of finished goods and supply inventories to meet the needs of our clients in the Continental Americas and abroad (Europe, Asia)
- Plan and schedule workflow of WIP for each department and operation according to previously established manufacturing sequences and takt times.
- Plan sequence of fabrication, assembly, outside processes, and other manufacturing operations for guidance of production workers and verification of correct routers to ensure most accurate takt time possible.
- Develop projections on rolling 3-6-12 month basis and monitor actual requirements versus projections.
- Implement takt time calculations and lean manufacturing concepts to identify waste and improve efficiency and performance of production lines.
- Generate production reports, Facilitate weekly meetings on project-production progress. Develop and distribute weekly schedules
- Participated in daily meetings to identify best practices and areas of inefficiency to form teams to investigate and recommended new processes or procedures.
Planner/Scheduler
Confidential - Houston, Texas
Responsibilities:
- Created schedules and maintained production orders within SAP to ensure manufacturing cycle times were obtained.
- Planned and managed production schedules for multiple product lines to meet customer delivery requirements
- Run analysis of sales order releases with respect to capacity planning and material requirements.
- Responsible for accurate routings to support production for multiple product lines
- Coordinated with engineering, production, quality and sales to achieve On Time Delivery.
Buyer/Planner/Scheduler
Confidential - Sugarland, Texas
Responsibilities:
- Planned, scheduled, and purchased a wide variety of materials required to make products to meet customer requirements.
- Managed all supplier related activities with the authority to commit company resources through contractual agreements for
- 12 different Baker facilities.
- Supported all plant purchasing functions through the SAP procurement process.
- Investigated and resolved AP issues with suppliers.
- Initiated, expedited and rescheduled purchased orders to meet demand requirements.
- Interfaced with external and internal customers and suppliers.