- As a senior project/program manager with many years’ experience managing complex IT infrastructure projects in many industries; challenges were overcome by building teams on a local, national and global presence.
- With projects ranging from hundreds of thousands to tens of millions of dollars in both government and private industries; meeting stringent deadlines while controlling budgets amongst cross - functional teams helped clients meet their business objectives that brought more earnings or cost savings to their bottom line.
PROFESSIONAL EXPERIENCE:
Confidential
Hammacher Schlemmer
Responsibilities:
- Brought on board with project six months behind schedule and after 4 weeks brought teams up to schedule within one week of their intended deadline
- As senior Project Manager with direct responsibility to executives of both firms; redefined business objectives with multiple service providers and telecommunications firms to align with client needs
- Determined contractual obligations with amendments to both vendors which better protected the client from unforeseen circumstances brought on by the vendors
- Helped drive solution for retrieval of archived d Confidential previously considered unavailable and saved client five years of call center history
Project Manager
Confidential
Responsibilities:
- Engaged as global PM for VoIP migration due to M&A activity in 14 countries
- Project lead for internal and external resources for department resource assignments, moves and changes to local site infrastructure design, layout, configuration and implementation
- Multi-million dollar P&L responsibilities for all VoIP network design, procurement and installations from 3rd-party and internal resources in Asia, Australia, Europe, Canada and U.S.
- Worked with local managers and executives’ departments to control time and budget for changes in IT infrastructure to meet business objectives of acquisition of new sites
- Design and support for all physical infrastructure for adding new teams to sites, merging old sites and upgrading VoIP infrastructure requirements for successful migration
- Finished project one month early