System Administrator Resume
Houston, TexaS
OBJECTIVE:
Looking for a Project Manager, Project Engineer, DCS Engineer, I&C Manager, Maintenance Manager or Instrumentation & Control Engineer position.
SUMMARY:
- Over (10) years of experience in design, FAT, SAT, Installation, Startup and Support of power plants associated with Oil & Gas facilities primarily using gas and steam turbines
- Over (10) years of SCADA Technology (coordinate SCADA project activities which include conceptual planning, design, development, installation, testing, and commissioning of SCADA related hardware and software systems; parties involved include vendors as well as internal customers, define requirements between operations applications and other real - time, on-line, and batch application processes throughout the company
- Over (20) years of experience a an Instrument Engineer
- Over (15) years specifying, installing, startup and support of analyzers and gas chromatographs
- Over (8) years specifying, installing, startup and supporting Citect products
- Over (2) years experience with Fisher Provox/CHIP computer interface.
- Over (5) years experience with Emerson DeltaV(specifying, detailed engineering, purchasing, FAT & SAT.
- Over (20) years of Commissioning hardware and software systems (participate and assist in the execution of equipment start-up, pre-functional testing, functional testing, and commissioning completion phases of a project, participate in the drafting of commissioning plans, pre-functional test checklists, functional test procedures, final commissioning reports and systems manuals, assist the Project Manager in creating project schedules, specification & system descriptions, problem solving, and conducting commissioning meetings assist the Project Manager in coordination with the Owner, Architect, Other Consultants, Owner's Representative, Construction Manager, General Contractor, and other subcontractors.
- Over (20) years of applications on Confidential TDC3000 including CL, LCN database creation, graphics building, logic configuration, equipment lists, equipment arbitration, virtual/alias names, PHD & Safety Manager. Over (5) years of experience Confidential PKS
- Over (20) years of experience in applying PLCs with a strong background in Allen-Bradley & Triconex
- Over (30) years of experience in process control specializing in batch applications
- Working knowledge of Six Sigma having worked under the direction of a Master Black Belt
- Extensive experience in system validation with emphasis on batch processes under S88, ISA standards in regulated FDA and CGMP compliance environments
- Over (10) years of Project Management for complete project lifecycle including budget justification, conceptual and detailed design, instrumentation specification/selection, programming of PLC/DCS/MMI, integrated system testing, startup/commissioning & final system acceptance
- Over (12) years of experience of applying Plant Data Historians with emphasis on AspenTech IP21/WEB21, Confidential PHD & OSISoft PI (SDK, Server, Datalink, It Monitor, DB Management, Data Interface, Client Displays, VB, VB.Net, Sigmafine)
- Over (5) years of working with Matrikon in developing OPC interfaces and have issued over $500,000 in purchase orders for developing custom software using their development tools.
- Working knowledge of Smart Signal Modeling for predictive failure in equipment. Package is very similar to those being supplied.
- Extensive experience in using Microsoft products including the Windows operating systems, Excel, Access, Project, Visio and SQL
- Experienced in programming in Visual Basic, VB.Net, Visual C & C++ and Pascal
- Strong background in TCPIP, OLE, OPC, ODBC & DDE technologies
- Thorough understanding of Oracle & other relational databases
- Extensive project engineering experience
- Construction management
- Working knowledge of ladder logic/function block
- Working knowledge of Boolean & analog control
- HMI & graphic development
- INTOOLS instrument data management
EXPERIENCE:
Confidential, Houston, Texas
System Administrator
Responsibilities:
- Communication/Data Handling primarily OPC (HDA).
- OSISoft PI Historians with approximately 75000 tags.
- Support of all Stakeholders.
- Production reports.
- HMI (RTWebParts).
- SQL and Oracle DBs
- ACE VisualBasic applications.
- For the wells, tag data retrieved primarily from SCADA systems.
- Another application is a Marathon proprietary advanced control application for drilling the wells to minimize the time it takes to complete. The first phase will be on (40) rigs.
- Support the SCADA/DCS systems.
- For offshore, the SCADA is broken into (2) parts, above water and below water.
Confidential
Instrumentation/Controls Commissioning Engineer
Responsibilities:
- My responsibility was for all OSBL work.
- It included Triconex for SIS, Omni for metering, Bentley Nevada for vibration, Siemens for boiler control and compressor control and several other PLC suppliers.
Confidential, Austin, Texas
System Engineer
Responsibilities:
- My contract involves supporting Rockell in their environmental compliance CEMS systems.
- I developed CEMS applications using PI to gather all environmental compliance information.
- The reason that they needed my expertise is because the system was not collecting the correct data in an appropriate time frame.
Confidential, Deer Park, Texas
PI System Engineer
Responsibilities:
- My primary responsibility was to correct the lost production data in PI when the inventory was "closed" at midnight.
- I rebuilt and redeveloped the PI application in order to ensure that the inventory would close out at midnight correctly.
- The network was not reliable and I was hired to resolve this particular issue.
Confidential, Pasadena, Texas
Controls Engineer
Responsibilities:
- My contract was necessitated by temporarily replacing a controls engineer.
- While there I gave support to the facility 24/7 as Controls Engineer For project work I had responsibility for commissioning (3) of their control rooms for an upgrade to Confidential . Work included (22) operators.
Confidential, Pasadena, Texas
Systems Analyst
Responsibilities:
- My task involved replacing six ABB gas chromatographs with four Confidential for their Catalloy facility.
- The controls reside on a Confidential TDC 3000 DCS.
- The control logic required modifying the existing CL procedures to support the new analyzers.
- I was responsible for doing all of the design work and integration of ….OSISoft PI involvement included adding/modifying the existing historian for all of the new data points and their integration into the Advanced Control package.
Confidential, Louisville, Kentucky
Controls Engineer
Responsibilities:
- My role was to replace some failed instrumentation and remove from the controls the fuel oil portion.
- It was a “duel fired” boiler and fuel oil was not being used.
- Responsible for the control philosophy for a project the required some pipelines to reverse their flow.
- This was necessitated due to a very high BTU (ethane) content of a new gas field.
Confidential, Phoenix, Arizona
Senior PI Technical Support Analyst
Responsibilities:
- Designed and wrote technical specifications the OSI PI system schedule and budget
- Installation of large screen monitors for the Gas Traders to monitor performance of the power plants.
- Developed reports on the over/under gas usage on an hourly/daily/monthly gas usage.
- Installed gas metering/totalizers on the gas feeds of the power plants to reconcile gas usage from the suppliers.
- Installed gas chromatographs on the gas feeds to the power plants to reconcile BTU content from the gas suppliers.
Confidential, Houston, Texas
Project Manager
Responsibilities:
- Responsible for all OSI PI design, development and support in addition to start up and acceptance testing.
- This was done for all projects. All projects included a historian, mostly OsiSoft PI interface.
- These projects were on gas turbines such as GE Mark 4, 5, and 6, compressors, and plant-wide.
- Performed a “study” comparing Foundation Fieldbus vs Profibus
- Developed “ITB” specifications for Cabinets, Foundation Fieldbus, Asset Manager, Process Automation System and Basic Process Control System, FAT/SAT testing requirements
- Reviewing Supplier Detailed Design issues for correctness to design criteria.
- Supported all field instrumentation being purchased from the suppliers.
- Reviewing Supplier Detailed Design issues using Intools for missing Instrument Data Sheets. When found, new data sheets are created using Intools.
- Site project/instrument/control engineer.
Confidential, Ferndale, Washington
Control System Engineer
Responsibilities:
- Work involved supporting the TDC installation moving to Confidential .
- It involved system support for the Aspen Tech historian.
- It also required support for the cogen facility with the plant supplying gas and receiving electricity with a SCADA system “tying” them together.
- VRU controls upgrade.
- Increase effluent system capacity.
- J5/J6 screw pump replacement and load center upgrade for the screw pumps and separator.
- Docks Instrument and Electrical upgrade
- Dock 54A&E rebuild.