Engineering Project Planner Resume
3.00/5 (Submit Your Rating)
PennsylvaniA
SUMMARY:
- Experience in project control, planning and scheduling with specialization in Engineering, Procurement, and Construction including subsea and offshore projects.
- Experienced at building project schedule from start to finish, schedule development, monitoring project progress, allocating and loading resources.
- Proficient in forecasting, earned value analysis, critical path analysis, and performance baseline measurement.
- Skilled at preparing progress reports and communicating across functional areas.
SKILL:
- Data Analysis & Primavera P6 Software
- Proficient in Word Perfect, Excel and Microsoft Project
- Efficient in PowerPoint, Critical Path Method
- PMI Scheduling (On - Going)
PROFESSIONAL EXPERIENCE:
Confidential, Pennsylvania
Engineering Project Planner
Responsibilities:
- Analyzed critical path and constraints to determine effect of changes to schedule and recommended work-around.
- Released various project schedule reports as required by project manager and become thoroughly familiar with all systems used to perform the job.
- Assigned resources to the project schedule as directed by Project Engineer and attended monthly resource meeting to analyze resource usage accordingly.
- Generated reports on resource manpower information for forecasting.
- Interfaced with clients and representatives to analyze critical path and recommended resolution.
- Rescued Project from extended shut down date and refined the schedule to the required level of detail to ensure schedule integrity and accuracy.
Planner/Scheduler
Responsibilities:
- Created milestones to identify the start of work including activities that required constraints.
- Loaded resources into the project resource wizard in Primavera P6, maintained and assigned baseline schedules for the project.
- Monitored and updated project progress on a routine basis against established scope, schedules and budgets.
- Identified critical activities and schedule variances that will put key milestone dates at risk and proposed remedial action plans.
- Communicated project status report to Project Management Team (PMT) and client on a
- Bi-weekly basis.
- Presented 60 Days look ahead to the project tram.
- Conducted Earn Value Analysis to generate reports on EV, SPI, CPI and EAC.
Project Planner / Scheduler
Responsibilities:
- Worked closely with Project Manager and assisted in facilitating planning workshops with department heads to build accurate schedules and baseline against the projects to be monitored.
- Created and maintained detailed drilling schedules based on Work Breakdown Structure(WBS) with task definitions, relationships, dependencies, activities codes and durations.
- Loaded resources into the project schedule with the resource wizard in Primavera P6 software, tracked project progress with schedule baseline and reported activities on critical path.
- Developed and maintained periodic status reports to keep management informed on project progress.
- Conducted schedule analysis to determine alternative courses of action on slipped schedule.
- Provide subject matters expertise in the area of critical path, earned value, variance and forecasting and communicated project status to Project Manager, team and the client
- Performed risk analysis, “what if” analysis and look ahead analysis to manage and focus resources and integrate different projects in the master schedule.
- Facilitated project schedule update meeting.