- Dedicated results driven Planner/Scheduler with several years’ experience in maintenance and construction in the petrochemical industry.
- Demonstrated success in project, turnaround, and maintenance planning/scheduling and project management with a commitment to completing projects on time and on budget.
- Strong communication, adaptability, leadership, customer focus, and decision - making skills with ability to manage commitments, innovation and change.
- Expertise in developing and motivating others, and facilitating consensus based on decisions through economical thinking.
- Proven strengths in building and fostering teamwork with team members and project stake holders.
- Expansive record of making contributions in fast-paced changing environments.
PROFESSIONAL EXPERIENCE
Confidential
Project Manager
Responsibilities:
- Estimated manpower, specified and procured materials and services, and linked relationships in SAP.
- Worked with project team, construction personnel, clients and stakeholders to develop and manage Prometheus maintenance schedule, involving large and complex construction activities.
- Performs weekly schedule update and generates progress reports for project team, clients and other stakeholders.
- Ensured that schedule is updated periodically, based on change orders, field performance, availability of construction materials and other factors that impact the project.
- Monitors status of activities and tracks progress. Identifies, reviews and escalates slippages and other potential schedule risks and issues. Works collaboratively with project team to effect remedial actions.
- Performed various P6 schedule operations, as was necessary to achieve project targets. This involved scope and logic modification, re-baseline, activity codes management, resource reassignment, duration re-estimation, look-ahead schedules.
Project scheduler
Confidential
Responsibilities:
- Worked with project team, construction personnel, clients and stakeholders to develop and manage P6 maintenance schedule, involving large and complex construction activities.
- Performs weekly schedule update and generates progress reports for project team, clients and other stakeholders.
- Ensures that schedule is updated periodically, based on change orders, field performance, availability of construction materials and other factors that impact the project.
- Monitors status of activities and tracks progress. Identifies, reviews and escalates slippages and other potential schedule risks and issues. Works collaboratively with project team to effect remedial actions.
- Performed various P6 schedule operations, as was necessary to achieve project targets. This involved scope and logic modification, re-baseline, activity codes management, resource reassignment, duration re-estimation, look-ahead schedules.
Project Scheduler
Confidential
Responsibilities:
- Worked with project team, construction personnel, clients and stakeholders to develop and manage P6 maintenance schedule, involving large and complex construction activities.
- Performs weekly schedule update and generates progress reports for project team, clients and other stakeholders.
- Ensures that schedule is updated periodically, based on change orders, field performance, availability of construction materials and other factors that impact the project.
- Monitors status of activities and tracks progress. Identifies, reviews and escalates slippages and other potential schedule risks and issues. Works collaboratively with project team to effect remedial actions.
- Performed various P6 schedule operations, as was necessary to achieve project targets. This involved scope and logic modification, re-baseline, activity codes management, resource reassignment, duration re-estimation, look-ahead schedules.
Senior Planning Engineer
Confidential
Responsibilities:
- Prepare baseline schedules and schedule basis documents for approval by project teams, performed critical path analysis.
- Prepare and provide schedule progress reports, trending charts and schedule analysis on a weekly basis.
- Verify schedule integrity and evaluate logic and float paths. Comply with Manufacturing scheduling practices and procedures.
- Facilitate project scheduling meetings and/or interactive planning meetings on a weekly basis. Monitor schedule deviations and variances and assist in the developing alternate methods for corrective action.
- Verify schedule integrity and evaluate logic and float paths. Participate in project and departmental meetings as required.
- Make recommendations to manage float and re-sequence activities to achieve project milestone dates and interim target completion dates.
- Analyze schedules from EP firms, Vendors and General Contractors. Analyze change orders for schedule impacts. Interface among project teams, stakeholders and other schedulers to assure schedule quality and use.
- Maintain record of scope changes, trends and variances that potentially affect schedule performance. Assure credibility of the information contained in the schedule.
- At the completion of the project, develop and record the project's historical schedule information and lessons learned for future use.
Planner/Scheduler
Confidential
Responsibilities:
- Plan and prioritize work for fast and efficient response. Create job packs, including all relevant information for job plans.
- Coordinate the development of work orders with Operations, Maintenance and Reliability personnel, while providing technical support for personnel on the SAP-PM module.
- Ensure proper documentation for work orders is in place. Identify material requirements and interfaces with vendor and/or supply chain as needed.
- Initiate Engineering Queries (EQs) for drawing and specification issues encountered in the field. Requests changes to procedures as required.
- Assists on budget development as required.
Project scheduler
ConfidentialResponsibilities:
- Responsible for maintaining and updating the project schedule utilizing P6 and coordinating I/E commissioning activities.
- Prepare baseline schedules and schedule basis documents for approval by project teams, performed critical path analysis.
- Prepare and provide schedule progress reports, trending charts and schedule analysis on a weekly basis.
- Verify schedule integrity and evaluate logic and float paths. Comply with Manufacturing scheduling practices and procedures.
- Facilitate project scheduling meetings and/or interactive planning meetings on a weekly basis. Monitor schedule deviations and variances and assist in the developing alternate methods for corrective action.
- Verify schedule integrity and evaluate logic and float paths. Participate in project and departmental meetings as required.
- Make recommendations to manage float and re-sequence activities to achieve project milestone dates and interim target completion dates.
- Analyze schedules from EP firms, Vendors and General Contractors. Analyze change orders for schedule impacts. Interface among project teams, stakeholders and other schedulers to assure schedule quality and use.
- Maintain record of scope changes, trends and variances that potentially affect schedule performance. Assure credibility of the information contained in the schedule.
Confidential
Project scheduler
Responsibilities:- Foster a safe work environment. Plan safety into every job.
- Maintain high ethical standards and level of professionalism
- Read and understand plant design drawings, plant specifications, vendor drawings, equipment drawings and field sketches
- Prepare accurate and detailed job plans through the use of field visits and interaction with the BP and contractor supervisors
- Develop detailed schedules for executing maintenance work orders and communicate them to the appropriate FGS and BP team members
- Communicate effectively with FGS management and BP supervision
- Assist the Lead Planner/Scheduler in developing and reporting performance metrics information
- Field verify material, equipment, tools and labor requirements for each job
- Requisition necessary maintenance materials required to perform planned job tasks. Ensure materials meet all applicable plant standards
- Maintain up to date work order backlog in SAP.
- Ensure historical information for each work order is entered into SAP.
- Other duties and responsibilities assigned by FGS management, and/or written into the FGS site maintenance planning procedure.
- Provide following information and assistance for unit cost forecasting/tracking:
- Communicate schedule and cost variances daily with assigned Performance Engineer.
- Ensure Performance Engineers are forwarded copies of daily, weekly and special schedules.
- Invite Performance Engineers to scheduling meetings, and meetings called for special projects.
- Forward copies of estimates for major job, unit, or equipment outages to the Performance Engineer for cost forecasting.